Project Timeline

Port Coquitlam City Council awarded the Design-Build contract for the Coast Meridian Overpass to SNC-Lavalin Constructors (Pacific) Inc. at a Special Council meeting on January 7, 2008. The contract took effect when it was signed by the partners on January 15, 2008.

The CMO opened to traffic on March 7, 2010.
  • Click here to view the construction staging timetable.

Coast Meridian Overpass timeline May 14 2007